Equinox Gold's Greenstone Project: On Schedule, On Budget

Alleen voor leden beschikbaar, wordt daarom gratis lid!

Overig advies 25/01/2023 15:44
All dollar amounts shown in United States dollars unless otherwise noted

VANCOUVER, BC , Jan. 25, 2023 /CNW/ - Equinox Gold Corp. (TSX: EQX) (NYSE American: EQX) is pleased to provide an update on construction progress at its Greenstone Project in Ontario, Canada. The Greenstone Project is being developed as a 60/40 partnership, respectively, by Equinox Gold and Orion Mine Finance Group and will be one of the largest gold mines in Canada, producing more than 400,000 ounces of gold annually for the first five years and more than five million ounces of gold over its initial 14-year mine life.

Greenstone construction progress is documented weekly in a photo gallery on Equinox Gold's website at www.equinoxgold.com and select photos are included in this news release.

Recent Highlights (at January 13, 2023 unless otherwise noted)

On schedule – The Greenstone Project is over 66% complete and on schedule to pour gold in the first half of 2024.
On budget – The Greenstone Project remains on budget. At December 31, 2022, 71% of total capital costs had been contracted and $680 million (55%) of the $1.23 billion construction budget had been spent (100% basis). Inflationary pressures have been mitigated through offsetting savings opportunities or absorbed through the $177 million contingency included in the construction budget.
Facilities completed – The construction team has completed the Ministry of Transportation (MTO) Patrol Yard, the Goldfield Creek diversion and the permanent effluent water treatment plant. The first four bays of the truck shop are complete and in use. The 14-km natural gas pipeline is complete and ready for commissioning in Q2 2023.
Equipment delivery continues to support the construction schedule, with key equipment on site or enroute.
Pre-production mining commenced ahead of schedule – The first four mining haul trucks and the first shovel were commissioned during Q3 2022 and mine pre-production activities got underway in September, ahead of schedule, with more than 2.5 million tonnes of material (ore, waste and overburden) mined to year-end 2022.

Greg Smith, President & CEO of Equinox Gold, commented: "The Greenstone Project is now more than two-thirds complete and remains on budget and on schedule. With key equipment on site or enroute, building infrastructure essentially complete and most buildings enclosed and heated, the construction effort is shifting to interior mechanical, electrical and piping installation during the winter months. Detailed commissioning and operation readiness planning is well underway to prepare for first gold pour in the first half of 2024."
Greenstone Project Progress

Area
see & read more on
https://www.equinoxgold.com/news/equinox-golds-greenstone-project-on-schedule-on-budget-20230125

Progress to Date (at January 13, 2023 unless otherwise noted)

Total Overall Progress



Overall project 66% complete and on schedule to pour gold in the first half of 2024
- Detailed engineering complete
- Procurement 77% complete
- Construction 56% complete

Safety


More than 2 million work hours completed with no lost-time injuries
Project to date, Total Recordable Injury Frequency Rate at December 31, 2022 of 3.57 per million hours worked

Budget


Project remains on budget. At December 31, 2022:
- 55% of total cost spent
- 71% of total cost contracted
- 30% of total cost awarded on a fixed cost basis

Earthworks, Concrete and Steel


Earthworks 73% complete (including plant site, tailings storage facility (TSF), Goldfield Creek diversion, Highway 11 realignment, water management infrastructure). Remaining earthworks include the TSF, which is ongoing, and the highway realignment and crushing area, which will recommence after the spring melt
Concrete 77% complete. Remainder includes the primary crusher slab on deck, high-pressure grinding roll (HPGR) pump box, west end process plant slab on grade and pre-leach thickening area
Structural steel 62% complete. Remainder includes the east end process plant and the HPGR building internal steel

Process Plant


Process plant 41% complete
Building enclosure and heating completed as planned for the process plant west end, power plant, secondary crusher and the ore bin tower portion of the HPGR building. The remainder of the HPGR building and east end process plant buildings are on schedule for enclosure in Q1 2023, which maintains the schedule
All mechanical, piping and electrical installation contracts awarded, installations underway
All eight leach tanks erected, mechanical installations underway

Equipment Delivery


All overseas and major equipment deliveries on track, including the primary and secondary crusher components, the apron feeder, conveyors, thickener and remaining prefabricated electrical rooms
All power plant equipment received
Ball mill delivery timing on track to start installation in March

Tailings Facility and Water Management


TSF 47% complete, south dams complete to the required elevation of 335.0 metres
Goldfield Creek diversion complete
Permanent effluent water treatment plant complete and commissioned

Power Plant and Electrical


Power plant 54% complete with all six gensets installed
Internal structural steel, walkways and platforms 86% complete; electrical and cable trays 30% complete
Natural gas pipeline complete and ready for commissioning

Site Infrastructure


Administration office, plant site fuel station and reagent cold storage buildings complete and operational
Sewage treatment plant complete and will be released to operations in Q1 2023; truck shop and warehouse 62% complete, first four bays of the truck shop are in use by the mine

Mobile Equipment and Mining


Mine pre-production activities operating 24/7 with more than 2.5 million tonnes of material moved in 2022
Four 250-tonne CAT 793F trucks, two Epicron D65 drills, one Komatsu PC5500 shovel and two Komatsu D475A-8 bulldozers were in use at year-end 2022
Commitment agreed on mobile equipment lease financing for $78 million, deferring approximately $53 million of initial capital spend (100% basis)

Infrastructure Repositioning


Highway 11 relocation 74% complete and progressing ahead of plan
New MTO Patrol Yard completed on time and handed over to the Ministry; demolition of the old facility is underway


Important Milestones

Construction during Q1 2023 will focus on completing enclosure of the HPGR and process plant east end buildings, receiving the majority of the remaining equipment, advancing mechanical, piping and electrical installations in the process plant and power plant buildings, and progressing the crushed ore storage and reclaim facilities. Four additional CAT 793F haul trucks, another Komatsu PC5500 shovel and another Komatsu D475A-8 bulldozer will be commissioned during Q1 2023, and the sewage treatment plant, potable water treatment plant and pit fuel station for mobile equipment will be commissioned and released to operations.

Important construction milestones include:

Independent QRA review of schedule and budget: June 2022
Process plant steel erection underway: June 2022
Administration building complete: July 2022
Delivery and assembly of pre-production fleet of four trucks and excavators: Q2-Q3 2022
Start of pre-production mining: September 2022
Permanent water effluent treatment commissioned: October 2022
Commence installation of gensets in power plant, power building enclosed: November 2022
Process plant west end, truck shop and SME plant building enclosed: December 2022
Leach tank erection and mechanical installations complete: Q1 2023
Ball mills received, commence installation: Q1 2023
Crushers installed, commence pre-commissioning of crushing circuit: Q3 2023
TSF complete and ready for use: Q4 2023
Highway 11 realignment complete: Q4 2023
Commence hot commissioning: Q1-Q2 2024
Gold pour: H1 2024

Equinox Gold Contacts

Greg Smith, President & CEO
Rhylin Bailie, Vice President, Investor Relations
Tel: +1 604-558-0560
Email: ir@equinoxgold.com



Beperkte weergave !
Leden hebben toegang tot meer informatie! Omdat u nog geen lid bent of niet staat ingelogd, ziet u nu een beperktere pagina. Wordt daarom GRATIS Lid of login met uw wachtwoord


Copyrights © 2000 by XEA.nl all rights reserved
Niets mag zonder toestemming van de redactie worden gekopieerd, linken naar deze pagina is wel toegestaan.


Copyrights © DEBELEGGERSADVISEUR.NL